Dismantle, tag, ship, reinstall — we’ve done this end-to-end for Minproc Engineers and others.
+61 3 9792 3555
Used & new power station equipment, moved with care.
Pacific Power Engineering (Aust) Pty Ltd is well versed in the removal and re-installation of used power station equipment and also new equipment. Many projects have been carried out successfully over the years — a list of some of these projects is below.
Selected installation projects
01
Engine Relocation
Mt Isa → Manila
Engine removal from Mt Isa, shipping and re-installation in Manila, Philippines.
02
Engine Relocation
Roseberry, Tasmania → Samoa
Engine removal from Roseberry in Tasmania, shipping and re-installation in Samoa.
03
Station Relocation
Windarra, WA → Ghana, Africa
Complete dismantle of 6 x K8 Mirrlees K Major engines, auxiliaries, all pipework and building — properly tagged and shipped from Windarra power station to a holding yard in Perth for Minproc Engineers who were to re-install the complete station in Ghana.
04
Pipework & Install
CAT 3516B, Tonga
Install and fabricate all pipework for CAT 3516B.
05
New Equipment
2 × New MAK 6MC32
Install and fabricate off-site all pipework for 2 new MAK 6MC32 engines.